Electric single-girder cranes have attracted an increasing number of customers by virtue of their advanced technology, light self-weight, compact structure, energy saving and low noise.
As large-scale mechanical equipment with a complex structure, cranes need to be assembled on-site after leaving the factory. It is well known that high-quality products can deliver optimal performance only with professional installation. Strict standardized requirements apply to the installation of electric single-girder cranes, which are specified as follows:
One side of the installed electric single-girder crane is equipped with a C-shaped rail, which serves to guide the flexible cable of the electric hoist. The crane traveling electrical control cabinet shall be mounted on the opposite side of the C-shaped rail.
The crane traveling electrical control cabinet shall be installed on the side close to the safety sliding contact line.
Direction definition: Standing on the C-shaped rail side and facing the crane, the forward and backward directions refer to the crane traveling direction, and the left and right directions refer to the trolley traveling direction.
For cranes equipped with only two crane traveling drive units, the drive units must be installed on the side where the C-shaped rail is mounted.
The crane traveling current collector shall be installed on the side close to the crane traveling motor.